ST. JOSEPH’S HOSPITAL
Empire Services • January 31, 2009
 
 JANUARY, 2009
Initially the bid date given was for an immediate start, but the award bid date was delayed for three months. Due to additional delays with permits and utilities the work did not start for an additional two months with the owner’s request that Empire’s work was to be completed and demobilized based on the original start date given.
The project required four buildings to remain standing, one being the original historic chapel located centrally among all of the demolition. Additionally, three exterior walls and a tower of the original stone structure had to remain independently intact to be incorporated into to the new proposed structure. This posed challenges that only a well organized team could conquer. One of the walls to remain was attached to the chapel and needed steel shoring with foundations in place for the wall to stand alone prior to separating and complete demolition of the remainder of the building. The tower and two other walls also required steel shoring. To erect the steel shoring, a JD80 Excavator needed to be crane lifted over the four story building and placed into the courtyard to excavate for the footers. Next, the concrete for the foundations had to be pumped into the interior of the courtyard. Then the steel shoring was partially assembled in the rear parking lot and lifted over the building and placed into the courtyard using a 300 ton hydraulic rock crane. The four buildings to remain were completely gutted of all interior finishes and mechanical systems to make way for the future Reading Citadel School. At the rear of the property, the prestressed 65,000 sq ft concrete parking garage was demolished and the resulting concrete from the garage, footers and walls were crushed and stockpiled on site to be used as future backfill material. All other demolition debris was hauled away using dumpsters and trailers to our sister company Berks Transfer to be recycled.
With all eyes on Empire as the Prime Contractor the project was accomplished with a team of over fifty laborers, five operating engineers, four foremen and a superintendent. At one point in the job there were over seventy workers on site between the subcontractors and Empire’s work force.
Empire utilized the services of various subcontractors to handle different aspects of the project such as electrical disconnects, capping, and relocation to keep temporary power in the buildings to remain. A sprinkler contractor was hired to separate systems and maintain fire protection operation as long as possible as per city codes. It was also necessary to rework standpipe systems so that the buildings to remain would have fire protection until such time as the new sprinklers were installed. Asbestos removal was a major portion of this project with thousands of feet of pipe insulation in the walls and underground tunnels as well as numerous areas of sprayed on fireproofing and transite panels. Thanks to the expertise of the asbestos contractor and their staff on site they were able to keep ahead of the demolition process and assist in adhering to the schedule. Empire hired both a structural steel and a foundation contractor to help in the underpinning and stabilization of existing sandstone walls of the original hospital structure to be salvaged and incorporated back into the new Reading Citadel School. Elk Environmental, a sister company of Empire Wrecking was contracted to explore, remediate, and secure any underground cisterns discovered during excavation.
In addition to all the subcontract work on this project, Empire had to complete over 200,000 sq ft of interior demolition which included the general hospital area, operating room and two large mechanical rooms. This had to be done without the use of motorized equipment due to the allowable floor loads of the buildings.
Prior to demolition, the first step was the remediation of all asbestos containing materials. This process along with the other subcontractors had to be coordinated to assure the schedule of twenty six weeks. By aggressive planning Empire Wrecking was able to complete the project two weeks ahead of schedule. This was possible because the Empire Wrecking team accelerated the pace by mobilizing additional equipment, with four excavators simultaneously excavating, hammering concrete, munching walls, and pulverizing footers . At the height of the project there were five sub contractors involved with the project and five different locations being worked on at the same time.
The demolition presented serious challenges. This was not a simple task as all of the buildings interconnected with other buildings – some of which were to stay and some which were to be taken down and still others that were to have just the exterior walls remain. This project utilized an experienced work force at these areas of separation. The only building that stood alone was a precast concrete parking garage. This part of the project was completed with the use of two 450 JD Ultra High excavators; a 300 Ultra High excavator, and numerous other equipment with grapples, hammers and processor attachments.
Empire completed the job including all change orders and the coordinating of additional asbestos, underground tank removals and over excavation of contaminated material and disposal on schedule. As always, Empire Wrecking Co. proved they were up to the Challenge
Since leaving the site the general package for renovating the remaining buildings and construction of the new school has been awarded to a General Contractor with Empire going back to the site once again for the final fit out as a subcontractor. This will consist of minor demolition, exterior wall openings, roof removals, new floor openings etc.
No one ever expects an emergency demolition situation—until it happens. Whether it’s a roof that suddenly caves in, walls that are crumbling                                                                    under the weight of age,                                                                    the aftermath of a fire or a severe weather event, the need for emergency demolition can arise without warning. That’s why hav                                               ing a reliable, experienced demolition                                              company ready to respond quickly is essential.                                                                                                            At Empire Services, we understand the critical importance of emergency demolition, not just for removing dangerous structures, but also for protecting the people and property around them. Here’s why emergency demolition is so vital and how we can keep your property and community safe during emergencies.
 
On behalf of the Empire Group, we would like to offer our sincere thanks to everyone who participated in our Annual Golf Classic on October 4                                  th                                               at the beautiful Galen Hall Golf Club in Wernersville, PA. It’s hard to believe this marked the 30th year of the tournament!                                                                                                                                     Although this was Empire Group's first time hosting the event at this historic venue, we have deep roots at Galen Hall —                                              Empire Services                                               demolished the original                                              Galen Hall Hotel                                               back in 1963 following a devastating fire. Since then, the golf club has remained a local landmark, known for its scenic views and welcoming atmosphere.                                                                                                                                     Despite the cool early morning, 99 golfers were warmed up and ready for the 8 AM shot gun start leading to some fun but competitive golfing. After the final putt dropped, everyone gathered for a hearty lunch followed by the award ceremonies. Shout out to the winners of all categories and the raffle!
 

This summer, Empire Services proved that even scorching heat can’t slow us down. Our demolition and excavation teams worked tirelessly across the region, keeping projects on schedule and ensuring client satisfaction. From precise pipe installations to complex industrial dismantling, we brought the talent, equipment, and dedication needed to deliver safe and successful results. Below are some of our recent project highlights that showcase the range of services Empire Services provides.
 
School demolition and sitework projects come with a unique set of challenges: tight timelines, limited space, sensitive environments, and the need to avoid disruptions to student learning. Whether it’s a complete building demolition or utility work, every site requires careful planning, coordination, and execution.                                                                                     At Empire Services, we understand the pressure and precision required in educational demolition projects. That’s why schools across Pennsylvania—from elementary to college campuses—trust us to get the job done right.
 

At Empire Services, we pride ourselves on taking on some of the most challenging industrial demolition projects in the region—and delivering safe, efficient, and precise results every time. One of our most recent projects in Delaware County, PA, exemplifies the level of experience, strategy, and innovation our team brings to the table.                                                                                                            Clarifying a Clarifier                                                                                                                         Clarifiers play a vital role in wastewater treatment by removing suspended solids through the process of gravity settling.                                                           These sedimentation                                              tanks                                               separate solid particulates from liquid, producing two distinct outputs: clarified water and concentrated sludge. Far from being just mechanical components, clarifiers are essential to the overall efficiency and success of any water or wastewater treatment system.                                                                                                                        Available in various shapes and sizes, most clarifiers are circular—an optimal design that promotes maximum settling efficiency. However, their large scale and unique structures can present challenges when it comes to access and maintenance. That’s why strategic planning is crucial when it comes time to dismantle these critical systems safely and effectively.                                                                                                            A Giant Shark Tank: Removing a 198-Foot Wastewater Clarifier                                                                                                            Empire Services was tasked with dismantling an enormous wastewater clarifier that stood 198 feet in diameter and 20 feet below ground level. The clarifier featured a complex interior slope and several built-in structures, making access a key challenge before demolition could even begin.                                                                                                            With most industrial demolition projects, the interior must be cleared before any exterior dismantling can occur. But in this case, even getting inside the structure required a creative solution. We used a small crane to lower a personnel lift                                                                      into the circular tank. Once inside, a custom scaffold stair tower was erected to ensure safe and easy access for crew members.                                                                                                            The personnel lift equipment was critical for enabling our team in torch-cutting the interior components located high inside the structure. These included:                                                                   Bridges                                                                                                             Motor systems                                                           Radial water troughs                                                           Walkways                                                           Internal steel frames                                                                                                                        From Demolishing to Salvaging                                                                                                            Whether it's removing massive industrial equipment, demolishing entire structures, or salvaging mechanical systems, Empire Services brings:                                                                   Advanced equipment                                                           Proven demolition techniques                                                           Highly trained crews                                                           A commitment to safety and efficiency                                                                                                                        This Delaware County project is just one example of how we go above and beyond to meet complex industrial demolition challenges.
 
At Empire Services, we specialize in transforming large, complex spaces - and few environments are more dynamic than today’s schools. We’re proud to take part in another                                              school renovation                                               in Berks County, PA, where we’re currently working on exciting renovation projects at                                              Governor Mifflin Middle School                                               and High School.
 
Ellen Ganime                                                                                                                         Not many people can say they’ve experienced the full arc of a company’s evolution in a single sitting; yet, I had the honor of doing just that while helping create a timeline for                                              Empire Group’s                                               70th anniversary. What began as a modest demolition and excavation firm (Empire Wrecking) has grown into a regional powerhouse (Empire Group) with five thriving affiliates, forever changing the landscape of Reading, PA, and beyond.                                                                                                                        From Demolition to Utility Work                                                                                                            It’s not just the Empire Wrecking (dba Empire Services) projects that are interesting—it’s also the affiliates (                                  Elk                                               Environmental Services,                                              DVC                                               ,                                              DVUC                                               , Empire Services, and                                              Berks Transfer                                  ) that were born out of necessity. Each one represents a solution to a challenge encountered on the job site. Over the years, these companies emerged organically, each one reinforcing the next while staying rooted in Empire Group’s foundational expertise. Seeing their formation laid out on the timeline, each connected to the Empire name, brings a swell of pride. Together, they form a tightly woven network that supports and enhances every project, expanding the company’s capabilities and impact.                                                                                                            A Journey Through the Decades                                                                                                            The timeline project is more than just compiling dates and milestones—it’s a journey through Empire Group’s living history. I had the pleasure of sitting down with former employees whose passion, dedication, and stories brought the company’s legacy to life. From dismantling a radio tower to demolishing a racetrack, their experiences painted a vivid picture of a company built on hard work, innovation, and camaraderie.                                                                                                            Former employees Bob Nocera and Steve Beisswanger shared unforgettable stories about complex projects and the bonds formed on job sites as we pored over countless pictures. Listening to them reminisce, it was clear: Empire Group isn’t just about the projects—it’s about the people and shared experiences that have played a crucial role in the company’s development.                                                                                                            A Legacy Etched in Steel and Stone                                                                                                                         What stood out most during the timeline creation was the scale and impact of Empire’s work. Old photographs showed the dramatic evolution of equipment and techniques—proof of how far the company has evolved. In many cases, Empire tackled projects so impressive in scale and complexity that they were featured in national publications, such as Demolition Magazine and Constructioneer,                                              as well as many various location publications.                                                                                                            More Than a Timeline—A Tribute                                                                                                            This timeline became more than a historical record; it became a tribute to the people and the progress that have defined Empire Group for over seven decades. It’s a reminder of the company’s roots, its remarkable growth, and the enduring spirit that continues to drive it forward.                                                                                                            As we celebrate this 70-year milestone, there’s a collective sense of pride in everything Empire Group has accomplished. From its humble beginnings to shaping skylines, the journey has been nothing short of inspiring. Here’s to 70 more years!
 
Empire Services is excited to play a key role in the transformation of Gingrich Library at Albright College in Reading, Pennsylvania. Constructed in 1964, Gingrich Library was once considered a modern structure. It has evolved over the decades to feature new technology and resources. Also, a fourth floor was added in 1977. This renovation will encapsulate today’s technology to create a unique learning facility. It will not only house the library but will also offer archives, a writing and tutoring center, and student disability services. Adding to the scope of work was an infrastructure issue; several areas of the building were compromised due to water infiltration causing concerning damage.
 
As summer rolls in, Empire Services is hard at work across Southeastern Pennsylvania, delivering top-tier demolition and excavation services with precision, safety, and efficiency. Our team proudly supports public and private projects that create lasting impacts, including transforming local parks. Here's a look at some of the exciting projects we're tackling this season.
 







